Proposed 2019 Annual Maintenance

Nieuws

The planned dates for our 2019 annual maintenance are now available. We propose to shut down at 06:00 CET (05:00 UKT) on 2 April 2019 for a period of 10 days, resuming flow at 06:00 CET (05:00 UKT) on 12 April 2019.

The closing date for any comments to the proposal is Friday 10 August 2018.

Contractually IUK has the right to 15 days maintenance. The proposed dates use 10 of those and it is too early to say if the other 5 will be required and if so, when/how those would be used.

Please send all responses to Consultation@interconnector.com.

See our media release for further information.

RSS