The following diagram illustrates the key dates of the incremental process

 

3 July 2023

 

28 August 2023

   

23 October 2023

Yearly
Capacity Auctions

(first Monday of July)          

 

Deadline submission of non-binding
demand indications

Start of work on DAR 2023

(8 weeks after Yearly Capacity Auction start)

 

   

Publication of DAR

- On Fluxys website
- On ENTSOG website

(16 weeks after Yearly Capacity Auction start)

 

       

Step 1 – Non-binding demand indications

Parties interested in incremental capacity can submit non-binding demand indications at any time. However in the 2023 market demand assessment, Fluxys considered non-binding demand indications submitted no later than 28 August 2023 (cob). Non-binding demand indications received after this deadline will be considered in the next market demand assessment – in 2025.

Non-binding demand indications can be submitted using the non-binding demand indications templates:

Fluxys Belgium

Download this form and send it to info.transport@fluxys.com.

Fluxys TENP & Deutschland

Download this form and send it to the TSO association FNB Gas.

Interconnector

Download this form and send it to consultation@interconnector.com



Step 2 – Demand Assessment Reports (DAR)

 

Fluxys
Company
IPs/Market Areas TSOs Document  
Fluxys Belgium ZTP-TTF Fluxys Belgium / GTS DAR ZTP-TTF 
Fluxys Belgium ZTPL-TTF Fluxys Belgium / GTS DAR ZTPL-TTF
Fluxys Belgium ZTP-PEG Fluxys Belgium / GRTgaz DAR ZTP-PEG
Fluxys Belgium ZTPL-PEG Fluxys Belgium / GRTgaz DAR ZTPL-PEG
Fluxys Belgium ZTP-THE
Fluxys Belgium / Fluxys TENP, Gascade, OGE, Thyssengas, Creos
DAR ZTP-THE
Fluxys Belgium ZTP-IZT Fluxys Belgium / Interconnector
DAR ZTP-INT

Fluxys Deutschland

THE-RU Fluxys Deutschland, GASCADE, Gasunie Deutschland, NEL Gastransport, ONTRAS Gastransport, OPAL Gastransport DAR THE-RU
Fluxys Deutschland
THE-N4G Fluxys Deutschland, GASCADE, ONTRAS Gastransport, Gasunie Deutschland, GRTGaz Deutschland, OGE / NET4gas

DAR THE-CZ           

Fluxys TENP THE-ZTP Fluxys TENP, GASCADE, OGE, Thyssengas, Creos / Fluxys Belgium
DAR THE-ZTP
Fluxys TENP THE-Switzerland Fluxys TENP, Terranets BW, OGE
DAR THE-CH
Fluxys TENP THE-TTF Fluxys TENP, GASCADE, Gasunie Deutschland, Thyssengas, Gastransport Nord, OGE / GTS
DAR THE-TTF
Interconnector IZT-ZTP Interconnector / Fluxys Belgium DAR INT-ZTP
Interconnector IBT-NGG Interconnector / National Gas Transmission DAR INT-NGT

Once the Demand Assessment reports are available you can also consult these on the ENTSOG website