Zelzate - Kallo

Why this project?

Fluxys is a key pioneer in the energy transition in Belgium.

That is why, in spring 2025, we started constructing a hydrogen pipeline between Zelzate and Kallo. Following a temporary interruption due to an appeal against the environmental permit, work resumed on 12 January 2026.

The new pipeline will connect the industrial clusters around the ports of Ghent and Antwerp. In this way, we are helping to build the infrastructure needed to transport hydrogen and supporting the development of a low-carbon industry.

The Zelzate-Kallo hydrogen pipeline is part of Belgium’s federal hydrogen strategy and the Flemish hydrogen vision. It is an important link in the further development of a hydrogen network in Belgium.

We are also exploring the possibilities for transporting CO₂ between Zelzate and Kallo. In this way, we aim to contribute to infrastructure that enables companies to reduce their CO₂ emissions and allows hydrogen and captured CO₂ to be transported between key industrial areas.

Facts and figures

  • The pipeline will be built on the territory of 9060 Zelzate, 9185 Wachtebeke, 9180 Moerbeke-Waas, 9190 Stekene, 9170 Sint-Gillis-Waas and 9120 Beveren.
  • Length of the pipeline: approximately 36 km
  • Diameter of the pipeline: 600 mm

Update of the environmental permit 

During construction of the hydrogen pipeline, dewatering is required at certain locations. Fluxys has therefore applied for an update of the existing environmental permit. The application relates exclusively to dewatering during the works. The pipeline route and the hydrogen pipeline itself remain unchanged.

Public consultation

A public consultation is being held for this update.

  • Start of the public consultation: 12 November 2026
  • File number: OMV-2026089036
  • Online information meeting: 18 November 2026 at 7:30 p.m.

Consultation

Landowners and operators have their own point of contact at Fluxys, from the preliminary study of a project to the restoration of a site following the construction of a pipeline. This allows them to consult with someone familiar with their concerns and the features of their land from the outset.

When? With whom? On what?
From Spring 2023 onwards
Landowners and operators Identification of and initial contact with the parties concerned
September 2023 Landowners and operators Information sessions presenting the project
After the start of the Declaration of Public Utility procedure Landowners Conclusion of easement agreements with the owners of land crossed by the pipeline
Before digging the trench Operators Production of a joint site description
Once the trench has been dug Operators Production of a description of any drainage present
After the restoration of drainage Operators Confirmation that drainage has been restored
After the restoration of the site(s) Operators Acceptance of the site(s) +
joint evaluation of damage and payment of compensation

Your Fluxys contact

Permit procedures

Permit procedure Status
Gewestelijk Ruimtelijk Uitvoeringsplan (GRUP)

On 7 June 2024, the Flemish government gave final approval to the conduit lane.
Additional information can be found on the website of the Flemish administration's Environment Department.

Declaration of Public Utility

The declaration of public utility was granted by royal decree on 15 December 2024.

Omgevingsvergunning (Building and environmental permit for the route in the Flemish Region)

The environmental permit was granted by ministerial decree on 31 January 2025. Following an appeal procedure and an agreement reached with the parties concerned, the permit is once again in force and work has resumed. Fluxys has applied for an update of the environmental permit.

Hydrogen transmission permit The hydrogen transmission permit was granted by ministerial decree on 6 March 2025.

Infosession environmental permit

Download the presentation of the infosession or a complete set of files with recordings of the session.