Pipeline Zeebrugge - Evergem

Why this infrastructure?

This project forms the second phase of the overarching Zeebrugge–Opwijk pipeline project. Find out more about the first phase: the Desteldonk–Opwijk project.

Additional capacity is needed in the Belgian grid to simultaneously cope with the loss of L-gas from the Netherlands, supply the new power plants that are coming into operation and maintain large flows to Germany. That's why Fluxys is preparing for the construction of a pipeline between Zeebrugge and Evergem. The missing link in the Belgian gas network is currently an efficient solution to ensure a continuous energy supply to Belgium and neighbouring countries.

Moreover, the construction of this pipeline is part of our long-term vision to prepare our energy system for the molecules of tomorrow. As demand for natural gas gradually declines over the coming decades, hydrogen is expected to play an increasingly important role in our network. By investing today in future-ready infrastructure, we create the flexibility needed to adapt parts of the network over time for the transport of hydrogen (or CO₂) when declining natural gas consumption creates room for this transition. In doing so, we support the development of a low-carbon energy system and strengthen Belgium’s role as a hub for Europe’s future energy flows. Find out more about how we are building hydrogen and CO₂ infrastructure for Belgium.

Fluxys is building this strategic pipeline in phases. For the section between Knokke-Heist and Evergem, via Lievegem, construction works started in 2025 and the pipeline is expected to be commissioned by the end of 2026. Final land restoration works will be completed in 2027. For the section between Zeebrugge and Knokke-Heist, construction is currently expected to start from 2031 onwards.

Facts and figures

  • The pipeline will run through Zeebrugge, Bruges, Knokke–Heist, Damme, Maldegem, Lievegem and Evergem.
  • Length of Zeebrugge–Evergem pipeline: 53 km
  • Diameter: 1,000 mm

A look at the construction works

Consultation

Landowners and operators have their own point of contact at Fluxys, from the preliminary study phase of the project through to the restoration of the site following the construction of the pipeline. This allows them to consult with someone familiar with their concerns and the features of their land from the outset.

When? With whom? On what?
From February 2023
Landowners and operators Identification of and initial contact with the parties concerned
From September 2023 Landowners and operators Information sessions presenting the project – the local residents concerned receive a personal invitation
After the start of the Declaration of Public Utility procedure (December 2023/January 2024) Landowners Conclusion of easement agreements with the owners of land crossed by the pipeline
Before opening up the working strip (early 2025) Operators Production of a joint site description
Once the trench has been dug Operators Description of presence and condition of drainage
After the restoration of drainage Operators Confirmation of restoration of the drainage
After the restoration of the site(s) Operators Site acceptance document + joint estimate of damage and payment of compensation

Information sessions

You can download the presentations from the various information sessions here:

Permit procedures

Permit procedure Public consultation Status
Declaration of Public Utility Delivered on 22/07/2024
Transmission permit   Delivered on 19/11/2024
Environmental permit
for pipeline section 
Zeebrugge-Lievegem
  Delivered on 24/01/2025
Environmental permit
for pipeline section
Lievegem-Evergem
Delivered on 26/02/2025

Information sessions

You can download the presentations as part of the application for an environmental permit: