Cost calculation methodology

    Cost calculation methodology for Non-Compatible gas production station

    To promote the injection of renewable gas into the transmission network, Fluxys Belgium supports these connections and facilitates the injection of Non-Compatible Gas in the following way:

    • Costs for the Injection Station: 50% covered by Fluxys Belgium and 50% covered by the producer, provided that it concerns the injection of green gas. In other cases, 100% covered by the producer.
    • Connection costs (pipeline): 100% covered by the producer.
    • Bank guarantee: The producer's share of the cost is covered by a bank guarantee corresponding to the transmission capacity to be booked for a period of 15 years.
    • Cash reimbursement: If the amount to be paid by the producer exceeds the value of the transmission capacity to be booked (at the regulated tariff) over a period of 15 years, this excess amount is covered by a cash payment. The cash portion covered by the producer will be reimbursed over a period of 15 years.
    • Electricity costs: The electricity costs for the Connection and Blending Station are covered by the producer.