Incremental Process 2017
The following diagram illustrates the key dates of the incremental process in 2017:
3 March 2017 |
6 April 2017 |
1 June 2017 |
27 July 2017 |
Annual Yearly Capacity Auctions | CAM NC 2.0 Entry into force | Submission of non-binding demand indications | Publication of DAR |

Step 1 – Non binding demand indications
Parties interested in incremental capacity could submit non-binding demand indications. However in the 2017 market demand assessment, Fluxys has considered non-binding demand indications submitted no later than 1 June 2017 (cob). Non-binding demand indications received after this deadline were considered in the next market demand assessment – either in 2019.
Non-binding demand indications could be submitted using the non-binding demand indications template.
Step 2 – Demand Assessment Reports (DAR)
Since 27 July 2017 the DAR of the different Fluxys Group companies are published at this location and on the ENTSOG website. For the German market the documents can be found on the FNBGas website.
IPs / Market Areas |
TSOs |
document |
H-gas TTF-ZTP | Fluxys Belgium / GTS | DAR TTF-ZTP |
L-gas TTF-ZTPL | Fluxys Belgium / GTS | DAR TTF-ZTPL |
H-gas ZTP-PEG | Fluxys Belgium / GRTgaz |
DAR ZTP-PEG |
L-gas ZTP-PEG | Fluxys Belgium / GRTgaz |
DAR ZTPL-PEG |
ZTP – GasPool |
Fluxys Belgium / Gascade |
DAR ZTP-GasPool |
ZTP – NCG |
Fluxys Belgium / OGE, Thyssengas, Fluxys TENP |
DAR ZTP-NCG |
IZT |
Fluxys Belgium / Interconnector UK ltd |
DAR IZT |
IBT | Interconnector UK Ltd / National Grid Gas plc | DAR IBT |