Maintenance FluxSwiss

Maintenance Works

Due to the maintenance activities planned by Transitgas during Gas Year 2019, FluxSwiss' capacities will be impacted as follows:

 

Gas Day FLUXSWISS
Firm Available Capacity
Affected Route
From To
21.05.2019 21.05.2019 70% Oltingue - Passo Gries
03.06.2019 04.06.2019 46%
27.08.2019 28.08.2019 70%
04.09.2019 06.09.2019 45%
09.09.2019 13.09.2019 42%

Gas Day FLUXSWISS
Firm Available Capacity
Affected Route
From To
23.05.2019 23.05.2019 60% Wallbach - Passo Gries
27.05.2019 28.05.2019 60%
03.06.2019 04.06.2019 43%
02.09.2019 03.09.2019 60%
04.09.2019 06.09.2019 44%
09.09.2019 13.09.2019 41%

Gas Day FLUXSWISS
reduced RF Capacity
Affected Route
From To
21.05.2019 21.05.2019 0% Passo Gries - Oltingue
&
Passo Gries - Wallbach
23.05.2019 23.05.2019 0%
27.05.2019 28.05.2019 0%
03.06.2019 04.06.2019 0%
27.08.2019 28.08.2019 0%
02.09.2019 06.09.2019 0%
09.09.2019 13.09.2019 0%

 

FluxSwiss reserves the right to change the affected periods and the relevant capacity restrictions, in compliance with applicable contractual provisions.

As our customer, you will be kept informed about such possible restrictions of transport capacities.

X

This site uses cookies

A cookie is a small file sent by the site server to your computer’s hard drive when you browse the website. The code contained in the cookie allows your computer to be recognised when you next visit the site.

The cookie is used to record your location and choice of language so that on subsequent visits the website appears automatically in your chosen language.

Cookie Policy
Confirm