Manage - Seneffe
Why this infrastructure?
If a new gas-fired power station is built in Manage, a new, 3.1-km high-pressure pipeline will be needed. The construction of the new pipeline is planned to start from the existing pipeline along the E19 motorway and would follow a route mainly in agricultural areas and in the future industrial zone.
The construction of the pipeline is scheduled for spring 2023 at the earliest (after the permits have been obtained) and will depend on which power stations will be chosen after the capacity supply auction to be held at the end of 2021. With the auction and the so-called capacity remuneration mechanism, the federal government wants to ensure that there is sufficient generation capacity available to meet electricity demand after the nuclear phase-out.
Consultation
Landowners and operators have their own point of contact at Fluxys, from the preliminary study of a project to the restoration of their land following the construction of a pipeline. This allows them to consult with someone familiar with their concerns and the features of their land from the outset.
Virtual info session
On 24 June 2021, Fluxys organised a virtual info session concerning this infrastructure. You can view the video below:
When? | With whom? | On what? |
---|---|---|
From October 2020 | Owners and operators | Identification of the relevant parties and initial contact |
Virtual info session on June 24 2021 | Owners and operators | Information meeting presenting the project – The local residents involved receive a personal invitation |
After the start of the 'declaration of public utility' procedure | Owners | Conclusion of a right of way agreement with the owners of the affected land |
Before work on the work area starts | Operators | Drafting of a site description, agreed by both sides |
After excavation of the trench | Operators | Description of any drainage |
After restoration of the drainage | Operators | Confirmation of restoration of the drainage |
After restoration of the land | Operators | Handover of the document for acceptance of the land, and assessment by both sides of damage and payment of compensation |
Permit procedures
Permit procedure | Status |
---|---|
Declaration of public utility | 11/2021 (submission) |
Planning permit (for the Walloon Region) | 11/2021 (submission) |
Transmission permit | 11/2021 (submission) |